SOLUTION: A painting job can be completed by 7 painters in 24 days. If 14 more painters join the team 9 days after starting work on the job, then how many more days are required to complete

Algebra.Com
Question 398033: A painting job can be completed by 7 painters in 24 days. If 14 more painters join the team 9 days after starting work on the job, then how many more days are required to complete the job?
can some one help solve this for me
thank you =)

Answer by solver91311(24713)   (Show Source): You can put this solution on YOUR website!


After 9 days, 15 days of work remain if no painters were added. Adding 14 painters to the original 7 painters means there are 3 times as many painters, hence they should get the remaining work done in one-third the time. 5 days.

John

My calculator said it, I believe it, that settles it
The Out Campaign: Scarlet Letter of Atheism


RELATED QUESTIONS

a painting job can be completed by 6 painters in 45 days if 24 more painters join the... (answered by ptaylor)
A painting job can be completed by 3 painters in 17 days. If 12 more painters join the... (answered by josmiceli)
a painting job can be completed by 7 painters in 17 days. if 21 more painters joined the... (answered by ankor@dixie-net.com)
a painting job can be finished in 8 painters in 23 days. if 24 painters join the team 7... (answered by ankor@dixie-net.com)
1. Kristen could shovel a large parking lot after a 12" snowfall in 5 hours. It would... (answered by 303795)
A Painting job can be completed in 12 hours by 3 professional painters. The same job can... (answered by josmiceli)
A team of 12 painters can paint a bridge in 20 days. How long would it take 1 painter?... (answered by ikleyn)
9 painters can paint 3 houses in a week. In how many days can 6 painters do the same... (answered by ewatrrr)
three men can complete a certain work in 7 days. after one day's work if three more men... (answered by ankor@dixie-net.com)