SOLUTION: twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop work. in how many days can the rest finish the work? (Show Your Solution)

Algebra.Com
Question 389832: twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop work. in how many days can the rest finish the work? (Show Your Solution)
Answer by Alan3354(69443)   (Show Source): You can put this solution on YOUR website!
twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop work. in how many days can the rest finish the work?
-----------------
The job is 24*38 man-days = 912 man-days
38*10 = 380 man-days done, 532 left
532 man-days/16 men = 33.25 days

RELATED QUESTIONS

15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how (answered by ikleyn)
15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how (answered by ankor@dixie-net.com)
if 6 men can do a piece of work in 20 day who many extra men should be engaged to do... (answered by macston)
if 20 men can do a piece of work in 8 days, then how many men can finish the same work in (answered by ankor@dixie-net.com)
7 men can do a piece of work in 12 days. How many men will be required to do double the... (answered by mbgupta@hotmail.com,ramkikk66)
a piece of work can be done in 34 days by 25 men. After 16 days, 10 men quit work. in... (answered by khwang)
If 6 men can do a piece of work in 14 days, how many men are needed to do the same work... (answered by tutorcecilia,ptaylor)
If 6 men can do a piece of work in 4 days, how many men are needed to do the work in 21... (answered by ankor@dixie-net.com)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in... (answered by stanbon)