SOLUTION: It takes 3 men 5 days to pave one mile of road. How long would it take 2 men to pave 10 miles?

Algebra.Com
Question 384108: It takes 3 men 5 days to pave one mile of road. How long would it take 2 men to pave 10 miles?
Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!

Hi,
Let x represent the time it would take for 2 men to pave the 10 miles
Question Sets Up the Proportion:
takes 3 men 5 days to pave 'one mile' of road, therefore:
It takes 5*10 or 50 days for 3 men to pave 10 miles.

Cross Multiply to solve for x
3x = 100
x = 33 1/3 days
RELATED QUESTIONS

Please help me solve this equation: It takes 4 men 16 hours to pave a footpath. How long... (answered by richwmiller)
It takes nine days for 8 worker to pave a stretch of road. If each worker works at the... (answered by Mathtut)
One road crew can pave a section of highway in 15 h. A second crew can do the same job in (answered by josgarithmetic,ikleyn,Alan3354,greenestamps)
if it takes 8 1/2 hours for 6 workers to pave 140 meters of road how many hours would it... (answered by ptaylor)
If a surfacing crew takes 167 seconds to pave 29 feet of asphalt, how many hours will it... (answered by solver91311)
It takes 20 workers a total of 30 days to pave a highway. How many days would it take 15... (answered by josgarithmetic,askhari139)
Each of two road graders can pave a certain section of the road in 15 hours working... (answered by stanbon)
If three men can pave six miles in four days, how much can each man pave in one... (answered by htmentor)
It takes 5 men to paint 2 identical houses in 3 days. Assuming that all men work at the... (answered by stanbon)