Question 358410: Six people to can perform a task in 8 days. If we add 2 equally able people, how long would it take?
Answer by mananth(16946)   (Show Source): You can put this solution on YOUR website!
6 people ----------- 8 days
8 people ------------?
indirect variation
6/8*8
= 6 days
...

RELATED QUESTIONS

If it takes 20 people to complete as task in 12 days. How many people will it take to... (answered by Edwin McCravy)
One person can complete a task in 3 minutes. A second person can complete the same task... (answered by ankor@dixie-net.com)
Six people can put a fence in 8 hours,how long would it take 1... (answered by Edwin McCravy)
Three people can complete a task in 3hr. 20min. How long would it take 4 people to... (answered by stanbon)
one person can complete a task 8 hours sooner than another person. working together both (answered by josmiceli)
if 8 people take 6 hours to complete a task how long it take 10 people to complete the... (answered by ankor@dixie-net.com)
two people are working on a task. Working alone, the first person could finish the task... (answered by ewatrrr)
If X people can do a job in D days, how long would it take Y people to do the same... (answered by Alan3354)
Hi I really need help with these questions please. Could someone show their solution too... (answered by richwmiller)