put this solution on YOUR website!1st belt Data:
time=12 min ; rate = 1/12 job/min
2nd belt Data:
time=9 min ; rate = 1/9 job/min
3rd belt Data:
time= x min ; rate = 1/x job/min
Together Data:
time= 3 min ; rate = 1/3 job/min
EQUATION:
rate + rate + rate= 1/3
1/12 + 1/9 + 1/x = 1/3
Multiply thru by 36x to get:
3x + 4x + 36 = 12x
5x=36
x=7.2 minutes (time for the 3rd belt working alone)