SOLUTION: If it takes 4 workers 15 months to build 10 houses. How many months will it take 3 workers to build 4 houses? They work at the same rate.
Algebra.Com
Question 316243: If it takes 4 workers 15 months to build 10 houses. How many months will it take 3 workers to build 4 houses? They work at the same rate.
Answer by vleith(2983) (Show Source): You can put this solution on YOUR website!
Set up a ratio
RELATED QUESTIONS
If it takes 3 days for 10 workers to finish building one house, how many days will it... (answered by scott8148,Edwin McCravy)
If it takes 3 days for 10 workers to finish a house, how many days will it take 15... (answered by ankor@dixie-net.com)
It takes 6 men 4 days to build 3 houses.
How many days do 10 men take to build 7... (answered by richwmiller)
It take 8 workers 7 days to build one house. 8:7:1
How long does it take 6 workers to (answered by josgarithmetic)
Problem:
It takes $1200$ workers $8$ years to build $3$ ziggurats. How many years would... (answered by fractalier)
If it takes 5 people 12 hours to paint 3 identical houses, then how many hours will it... (answered by josgarithmetic)
How many houses can 10 people build if:
a) it takes a team of 3 people to build each... (answered by KMST)
Please help me solve the following problem:
If it takes 80 workers 10 days to build 12... (answered by ewatrrr)
if 6 workers can build 4 cars in two days then how many days would it take 8 workers to... (answered by oberobic,ankor@dixie-net.com)