SOLUTION: A building contractor employs a master mason, a journeyman mason and an apprentice mason.
The master mason and the journeyman working together can finish a brick wall in 10 hours.
Algebra.Com
Question 313753: A building contractor employs a master mason, a journeyman mason and an apprentice mason.
The master mason and the journeyman working together can finish a brick wall in 10 hours. It
takes the master and apprentice 12 hours to do the same job, while the journeyman and apprentice
require 15 hours to complete the task.
If all three work together, how long does it take to build the wall?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
A building contractor employs a master mason, a journeyman mason and an apprentice mason.
The master mason and the journeyman working together can finish a brick wall in 10 hours.
It takes the master and apprentice 12 hours to do the same job,
while the journeyman and apprentice require 15 hours to complete the task.
:
Find how many hrs each require working alone
:
Let the individual times of the three masons be: m, j, a
:
Let the completed job = 1
:
Write an equation for each statement:
:
"The master mason and the journeyman working together can finish a brick wall in 10 hours"
Eq1: + = 1
:
"It takes the master and apprentice 12 hours to do the same job,"
Eq2: + = 1
:
"the journeyman and apprentice require 15 hours to complete the task."
Eq3: + = 1
:
Multiply Eq1 by 6 and Eq2 by 5:
+ = 6
+ = 5
-------------------------------Subtraction eliminates m, so we have
- = 1
:
Multiply eq3 by 4 and add to the above equation
- = 1
+ = 4
----------------------------- adding eliminates a, find j
= 5
5j = 120
j =
j = 24 hrs to do the job alone
:
Substitute 24 for j in eq1, find m
+ = 1
Multiply by 24m
10(24) + 10m = 24m
240 = 24m - 10m
m =
m = 17.14 hrs to do the job alone
:
Using eq3, find a
+ = 1
Multiply by 24a
15a + 15(24) = 24a
360 = 24a - 15a
a =
a = 40 hrs to do the job alone
:
Summarize: a = 40; j = 24; m = 17.14 hrs
:
"If all three work together, how long does it take to build the wall?"
Let t = time required when all three work together
+ + = 1
multiply equation by 17.14*24*40 = 16454.4, results:
960t + 685.6t + 411.36t = 16454.4
2056.96t = 16454.4
t =
t ~ 8 hrs all three working
;
:
Check solution using a calc:
8/17.14 + 8/24 + 8/40 =
.467 + .333 + .2 = 1
RELATED QUESTIONS
An apprentice mason takes 8h longer to build a small fireplace than an experienced mason. (answered by Paul)
A mason can lay the bricks in a sidewalk in 12 hours. The mason's apprentice requires 16 (answered by stanbon)
A mason can lay the bricks in a sidewalk in 14 hours. The mason's apprentice requires 22... (answered by jorel1380)
A mason can lay the bricks in a sidewalk in 10 hours. The mason's apprentice requires 12... (answered by rothauserc)
A brick mason requires 12 hours to lay a garden wall by himself. After the mason and his... (answered by richwmiller)
A mason and his assistant work on a fireplace for 6 hours together. Then the mason... (answered by Boreal)
A crew consists of 1 apprentice, 1 journeyman, and 1 master carpenter. The crew receives... (answered by josmiceli)
A crew consists of 1 apprentice, 1 journeyman, and 1 master carpenter. The crew receives (answered by ankor@dixie-net.com)
A crew consists of 1 apprentice, 1 journeyman, and 1 master carpenter. The crew receives... (answered by josgarithmetic)