SOLUTION: A completes one work in20 days. B cmpletes the same work in 25 days while C completes the same in 30 days. If intially A started the work and after 4 days he quit it. Next B carry

Algebra.Com
Question 309762: A completes one work in20 days. B cmpletes the same work in 25 days while C completes the same in 30 days. If intially A started the work and after 4 days he quit it. Next B carry forward the work & he copleted the half of the remaining work then how in how many days the C will cmplete the remaining work?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
A completes one work in 20 days.
B cmpletes the same work in 25 days
while C completes the same in 30 days.
:
If initially A started the work and after 4 days he quits it.
Next B carry forward the work & he completed the half of the remaining work
then how in how many days the C will complete the remaining work?
:
Let the completed work = 1
:
A does = ; remains
:
B does * = remains
:
=
cross multiply
5C = 60
C =
C = 12 days to complete it
:
:
Check
A does
B does
C does
-----------------
total 1

RELATED QUESTIONS

If A completes a particular work in 4 days and B the same work in 12 days. How many days... (answered by richwmiller)
ASHA COMPLETES A WORK IN 10 DAYS AND BEENA DOES THE SAME WORK IN 15 DAYS. IN HOW MANY... (answered by josmiceli)
10 men completed a construction work in 11 days,15 men completes the same type of... (answered by josmiceli)
if a man completes a work in 9 days,second man complete work in 7 days and 3 mens... (answered by ankor@dixie-net.com)
if 6 women & 10 children completes the work in 6 days , and 6 Women alone completes the... (answered by ptaylor)
A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A (answered by htmentor)
A and B can do a piece of work in 6 days,B and c together in 10 days,c and A together in... (answered by lwsshak3)
Maria takes 9 days to complete a piece of work.John takes 3 days to complete the same... (answered by stanbon)
: if a worker completes its work 939 meters in 30 days. how many meters of work will he... (answered by macston)