SOLUTION: 25 workers could finish a job in 8 days. 2 days into the job, 7 leave. how long will it take for the remaining 18 to finish the job?

Algebra.Com
Question 305682: 25 workers could finish a job in 8 days. 2 days into the job, 7 leave. how long will it take for the remaining 18 to finish the job?
Answer by Alan3354(69443)   (Show Source): You can put this solution on YOUR website!
25 workers could finish a job in 8 days. 2 days into the job, 7 leave. how long will it take for the remaining 18 to finish the job?
--------------
The job is 200 man-days (igoring age and gender)
25*2 = 50, leaving 150 man-days
150/18 = 25/3 days

RELATED QUESTIONS

A team of 25 engineer were to build a fence, they could complete the job in 8 days. 2... (answered by edjones)
If 3 people finish a given job in 8 days,how many days will it take for 2 people to... (answered by ptaylor)
3 workers can do a job in 36 days. How long would it take 2 workers to finish the same... (answered by macston,Edwin McCravy)
A job can be done by 25 men in 32 days. After 8 days, 5 men left. how long will it take... (answered by AnlytcPhil,richwmiller,MathTherapy)
20 artisans can accomplish a job in 30 straight days, 25 artisans were hired at the... (answered by josgarithmetic)
20 artisans can accomplish a job in 30 straight days, 25 artisans were hired at the... (answered by jorel1380)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
i have solved that if Worker A finishes a job in 8 days and worker B finishes it in 12... (answered by josmiceli)
Joshua can finish a certain job in 4 days while Kevin can finish the same job in 2 days.... (answered by stanbon)