SOLUTION: how to solve sam can do a work in 3 days and john can do that work in 5 days,how many days they will take to finish that work if work togather?

Algebra.Com
Question 297627: how to solve sam can do a work in 3 days and john can do that work in 5 days,how many days they will take to finish that work if work togather?
Found 2 solutions by vleith, richwmiller:
Answer by vleith(2983)   (Show Source): You can put this solution on YOUR website!
The way I like to do these is to look at each one's daily rate. Then add their daily rate to see how they can work together.
So Sam can do 1/3 of the job in a day (so he takes 3 days to do the job alone)
John can do 1/5 of the job in a day (it take him 5 days to do the whole thing)
Together, their daily rate is = =
So they can do over half the job in a ay
To do the whole job

1 job is a whole job done once

So working together they can do the job in 1 and 7/8's days.
Make sense now?

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
x/3+x/5=1
x is a the time it takes them working together
1 is one job
x/3 is the part of the job that Sam does
x/5 is the part of the job that John does
multiply by 15
5x+3x=15
8x=15
x=15/8
x= 1 7/8 days to do the job together
7/8*24=21 hours
x=1 day and 21 hours to do the job together
check
15/8/3+15/8/5=1
5/8+3/8=1
Sam does 5/8 of the job and john does 3/8
ok

RELATED QUESTIONS

Joel can finish a work in 10 days, after he has worked for 2 days, Sam came to help him... (answered by richwmiller)
Bigyan can do  of a work in 9 days. He calls Amar to finish the remaining work. They work (answered by Collinwilfixyouuprealnice)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ptaylor)
If sam can do a job in 4 days that Lisa can do in 6 days, and Tom can do in 2 days, how... (answered by nerdybill)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)
Sam and Justin together can do a work in 2 days. If they had to work separately, the time (answered by josgarithmetic,ikleyn)
sam and justin together can do a work in 2 days. if they had to work separately, the time (answered by josgarithmetic)
sam and justin together can do a work in 2 days. if they had to work separately, the time (answered by josgarithmetic)
Tom takes 3 days to do a piece of work while jerry takes only one day for the same.... (answered by ikleyn)