SOLUTION: An old conveyor belt takes 21 h to move one day's coal output from the mine to a rail line. A new belt can do it in 15 h. How long does it take when both are used at the same time?

Algebra.Com
Question 281137: An old conveyor belt takes 21 h to move one day's coal output from the mine to a rail line. A new belt can do it in 15 h. How long does it take when both are used at the same time?
Please help. I've seriously spent about an hour trying to set this up and I can't, well I just haven't been able to yet.

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
x/21+x/15=1
x/3*7+x/3*5
5x/3*7*5+7x/3*5*7=1
5x/105+7x/105=1
12x/105=1
4x=35
x=35/4
x=8.75 hours


RELATED QUESTIONS

It's late here and I can't figure out how to start this. I did the crane off loading... (answered by ptaylor)
An old conveyor belt can move one day's coal output in 21h. A new belt can move one day's (answered by nerdybill)
Conveyor belt # 1 can move 1,000 boxes in 8 minutes. Conveyor belt #2 can move 1,000... (answered by mananth)
In 2 minutes, a conveyor belt can move 300 pounds of recyclable aluminum from the... (answered by robertb)
One conveyor belt can move 1000 boxes in 12 minutes. Another can move 1000 boxes in 10... (answered by ankor@dixie-net.com)
One conveyor belt can move 1000 boxes in 11 minutes. Another can move 1000 boxes in 3... (answered by greenestamps,josgarithmetic)
One conveyor belt can move 1000 boxes in 12 minutes. Another can move 1000 boxes in 9... (answered by stanbon)
In three minutes a conveyor belt moves 800 pounds of recyclable aluminum from a delivery... (answered by Alan3354)