Question 262229: A company contracts to paint 3 houses. Mr.Brown can paint a house in 6 days while Mr.Black would take 8 days and Mr.Blue 12 days. After 8 days Mr.Brown goes on vacation and Mr. Black begins to work for a period of 6 days. How many days will it take Mr.Blue to complete the contract?
A. 7 B. 8 C. 11 D. 12

Answer by drk(1908)   (Show Source): You can put this solution on YOUR website!
we have a working together problem. Here is an equation to start us out:

step 1 - multiply by common denominator of 24 to get

adding we get

subtract 50 to get

divide by 2 to get

RELATED QUESTIONS

A company contracts to paint 3 houses. Mr.Orange can paint a house in 6 days while... (answered by lynnlo)
Snowhite Paint Co. contracts to paint three houses. Andy can paint a house in 6 days,... (answered by richwmiller)
Mr. Mann can lay a walk in 6 days, and Mr. Gregory in 8 days. How long will it take Mr.... (answered by TimothyLamb,MathTherapy)
solve. Round to the nearest tenth of necessary Mr. Endicott, Mr. Bookout, and Mr.... (answered by Theo)
Sam can paint a house in 5 days by himself, while Betty can paint the same house in 20... (answered by richwmiller)
Mr Udofoa can clear a field on 6 days while Mr udo can clear the same field in 3 days.... (answered by josgarithmetic,ikleyn)
6 men can paint a house in 8 days. How long would 4 men... (answered by richwmiller)
4 painters can paint a house in 3 days, at this rate, how many houses can 6 painters... (answered by josmiceli)
If 4 painters can paint a house in 9 days,how many days would it take 6 painters to paint (answered by amoresroy)