SOLUTION: A certain job has been estimated to take 10 men 5days. On day 4, half of the job has been completed. How many additional men must be addd to the crew in order to complete the job o

Algebra.Com
Question 253386: A certain job has been estimated to take 10 men 5days. On day 4, half of the job has been completed. How many additional men must be addd to the crew in order to complete the job on time?
Answer by palanisamy(496)   (Show Source): You can put this solution on YOUR website!
A certain job has been estimated to take 10 men 5days.
So the total number of mendays = 10*5 = 50
On day 4 half the job has been completed.
That means 25 mendays has been completed.
The remaining mendays = 50-25 = 25
In order to complete the work on the fifth day 25 men have to do work.
Therefore the number of additional men required = 25-10 = 15

RELATED QUESTIONS

Ray has completed three-fifths of a construction job and he has been on the job for 117... (answered by richwmiller)
10 Men begin to work together on a job, but after some days, 4 of them left the job. As a (answered by josmiceli)
After a certain number of men had been employed on a job for 24 days and had finished... (answered by ewatrrr,josmiceli)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
Five workers have been hired to complete a job. If one additional worker is hired, they... (answered by Edwin McCravy,math_tutor2020,josgarithmetic,ikleyn)
how to solve Marcus and Will are painting a barn. Marcus paints twice as fast as Will.... (answered by josgarithmetic)
Marcus and Will are painting a barn. Marcus paints twice as fast as Will. On the first... (answered by josgarithmetic)
Five workers have been hired to complete a job. If one additional worker is hired, they... (answered by ikleyn,math_tutor2020)
40 men can complete a piece of work in 40 days.They started the work together. But at the (answered by josgarithmetic)