SOLUTION: if it takes 4 men 12 days to dig a hole, how long would it take 6 men?

Algebra.Com
Question 248615: if it takes 4 men 12 days to dig a hole, how long would it take 6 men?
Answer by ptaylor(2198)   (Show Source): You can put this solution on YOUR website!
if it takes 4 men 12 days to dig a hole, how long would it take 6 men?
It takes 4X12=48 man-days to dig the hole (i.e. 1 man could dig the hole in 48 days)
1 man----48 days
2 men -----24 days
3 men-------16 days
4 men-------12 days
5 men ----9 3/5 days
6 men -----8 days
Another way to look at this problem:
Let x=amount of time it takes 6 men to dig the hole
4 men work at the rate of 1/12 hole per day
1 man works at the rate of 1/48 hole per day
6 men works at the rate of 6/48 hole per day
So, our equation to solve is:
(6/48)x=1 (1 hole, that is)
6x=48
x=8 days
Hope this helps---ptaylor

RELATED QUESTIONS

if 4 men work for 6 hours a day for 3 days to dig a hole. how long will it take 12 men to (answered by macston)
If it takes 6 men 4 days to dig a hole 3 metres deep, how long will it take for 10 men to (answered by josgarithmetic,ikleyn)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
If it takes 3 men 4 days to dig a drain how long would it take... (answered by josgarithmetic)
if it takes 7 men 3 hours to dig a hole, how long will it take 2 men ? (answered by josmiceli)
If it takes 6 men 6 days to dig 6 holes, how long would it take 100 men to dig 50... (answered by Alan3354)
If 3 men take 4 days to dig a drain how long would it take 2 men (answered by josgarithmetic)
if it takes 8 men 9 days to dig a tunnel how long will it take 6 men to dig the same... (answered by ikleyn)
If it takes two men three hours to dig a hole 4 meter long, four meters wide, and four... (answered by god2012)