SOLUTION: A clerk can process 350 forms in 2 3/5 days. It takes 1 2/3 days for another clerk to process the same 350 forms. If both clerks work together, how long will it take them to proces
Algebra.Com
Question 246035: A clerk can process 350 forms in 2 3/5 days. It takes 1 2/3 days for another clerk to process the same 350 forms. If both clerks work together, how long will it take them to process the 350 forms?
I have tried to work it out and got the following:
Clerk 1 can do 350/(13/5) forms per day = 1750/13 forms per day
Clerk 2 can do 350/(5/3) forms per day = 1050/5 forms per day
I have no idea where to go from there as the bases aren't equal and I'm not sure if I went about it correctly to begin with :| Any help is greatly appreciated!
Answer by marcsam823(57) (Show Source): You can put this solution on YOUR website!
Let x = the total number of days it will take both clerks to do the job
Convert both mixed numbers to fractions:
Clerk 1 can do the job in 2 3/5 or 13/5 days
Clerk 2 can do the job in 1 2/3 or 5/3 days
This type of problem can be tricky because it requires a bit of a leap in logic. The key to this problem is determining what fraction of the job each clerk can do in one day and adding those two numbers together.
Clerk 1 can do the job in 13/5 days
In one day Clerk 1 can do 1/ 13/5 or 5/13 of the job
Clerk 2 can do the job in 5/3 days
In one day Clerk 2 can do 1 / 5/3 or 3/5 of the job
(Note that "the job" = processing 350 papers; the 350 is not actually used in the computation at all!)
Set up the equation
Processing 350 forms represents completing 100% of the job or completing 1 job.
Below is the equation in words and the equation with the values from above:
(portion of the job completed in one day by Clerk 1 + portion of the job completed in one day by Clerk 2) x (total number of days) = 1 complete job
Find the common denominator and add:
x = 1 1/64 (one and one sixty-fourth) or 1.01 days
Here is another example of this type of problem using simpler numbers.
Painter 1 can paint a fence in 2 days
Painter 2 can paint the same in fence in 5 days
How long will it take if they work together?
Using our formula from above:
Painter 1 can do the job in 2 days
In one day Painter 1 can do 1/2 of the job
Painter 2 can do the job in 5 days
In one day Painter 2 can do 1 /5 of the job
Set up the equation:
Find the common denominator and add:
x = 1 3/7 (one and three sevenths)or 1.42 days(about a day and a half)
RELATED QUESTIONS
it takes an experienced clerk 9 days to process the mailing of annual forms it takes a... (answered by Cromlix)
A clerk can process a form in 15 minutes. How many forms can that clerk process in six... (answered by ramkikk66)
1.Arthur can process 300 forms per hour, whereas Lewis can process 200 forms per hour.... (answered by richwmiller)
A clerk can complete a job in 4 hours. Another clerk can do the same job in 2 hours.... (answered by checkley71)
If one clerk can process 75 pieces of mail in 2 and 1/2 hours, how long will it take... (answered by checkley77)
if one clerk can process 75 pieces of mail in 2 and 1/2 hours, how long will it take... (answered by ankor@dixie-net.com)
If one clerk can process 75 pieces of mail in 2 and 1/2 hours, how long will it take... (answered by josmiceli)
Clerk A can process 50 applications in 4 hours, and clerk B can process 50 applications... (answered by nerdybill)
A large biotech firm uses two computers to process the daily results of its research... (answered by ikleyn)