it takes 15 workers to build 500 feet of fencing in 6 hours. At this rate, how many workers are needed to build 1000 feet of fencing in 9 hours
It takes 15 workers to build 500 feet of fencing in 6 hours.
Doubling the workers doubles the fencing in the same time. Therefore,
it takes 30 workers to build 1000 feet of fencing in 6 hours.
Doubling the workers halves the time for the same amount of fencing. Therefore,
It takes 60 workers to build 1000 feet of fencing in 3 hours.
Using only one-third as many workers triples the time for the same
amount of fencing. Therefore,
It takes 20 workers to build 1000 feet of fencing in 9 hours.
Edwin