SOLUTION: If she works 8 hours a day, nancy can paint a house in 12 days. if she works only 6 hours a day , the number of days it would take her to paint the same house , working at the s

Algebra.Com
Question 200592: If she works 8 hours a day, nancy can paint a house in 12 days. if she works only 6 hours a day , the number of days it would take her to paint the same house , working at the same rate is
a) 96 b) 16) c) 9 d) 48) e) 72

Answer by checkley77(12844)   (Show Source): You can put this solution on YOUR website!
8*12=96 hours to paint the house.
96/6=16 days to paint the house.
Answer b).

RELATED QUESTIONS

Working 8 hours a day, Chris Champ can paint a house in 12 days. If Chris works only 6... (answered by amnd)
If a woman works for 3 1/2 hours per day, she can finish a piece of work in 10 days. How... (answered by Theo)
A and B can paint a certain house if A works 6 days and B works 12 days, or they can... (answered by richwmiller)
Joe can paint his house by himself in 4 days. His wife needs an additional day to... (answered by josgarithmetic)
ely santos is working part time at a restaurant in makati. if she works for 30 hours in... (answered by solver91311)
Maria is a student assistant at the mathematics department. Since she is hardworking and... (answered by Theo)
Maria is a student assistant at the mathematics department. Since she is hardworking and... (answered by CubeyThePenguin)
If Jane volunteered at the hospital 12 hours in January and each day she works 4/5 an... (answered by stanbon)
paul paint his house in 12 days if works 8hr/day. how many day he will take to paint if... (answered by Engg.N Magampon)