SOLUTION: Four men can dig a 40 foot well in 4 days. How long would it take for 8 men to dig a 60 foot well?
Algebra.Com
Question 199674: Four men can dig a 40 foot well in 4 days. How long would it take for 8 men to dig a 60 foot well?
Found 2 solutions by Alan3354, ankor@dixie-net.com:
Answer by Alan3354(69443) (Show Source): You can put this solution on YOUR website!
Four men can dig a 40 foot well in 4 days. How long would it take for 8 men to dig a 60 foot well?
----------------
A 60 ft well would take the original 4 men 1.5 times as long, or 6 days.
Having 2x as many men cuts that in 1/2, so it's:
3 days.
----------
(4 days * 1.5)/2 = 3 days
--------------
This all assumes that there is room for 8 men to work at the bottom of the hole without getting in each other's way, which is not likely.
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
Four men can dig a 40 foot well in 4 days.
How long would it take for 8 men to dig a 60 foot well?
:
Find how many man-days required to dig a 40 ft well:
4 * 4 = 16 man-days
:
Let x = no. of days to dig the 60 ft well
:
Use a ratio equation:
=
Simplify
=
Cross multiply
40x = 2*60
40x =
x = 3 days, 8 men dig a 60 ft well
:
:
RELATED QUESTIONS
4 men or 6 boys can dig a well in 14 days . how long would 2 men and 4 boys take to dig... (answered by ankor@dixie-net.com)
If 3 men take 4 days to dig a drain how long would it take 2 men
(answered by josgarithmetic)
if it takes 4 men 12 days to dig a hole, how long would it take 6... (answered by ptaylor)
if 4 men work for 6 hours a day for 3 days to dig a hole. how long will it take 12 men to (answered by macston)
If 12 men can dig a trench in 8 days how many men can dig it in 6... (answered by josgarithmetic,greenestamps)
If 12 men can dig 35 holes in 14 days,
(a) how many men are needed to dig 35 holes in 8... (answered by Alan3354,jorel1380)
8 men can dig a garden in 20 days. After working for 5days, 3men left. How long will it... (answered by josmiceli)
If it takes 3 men 4 days to dig a drain how long would it take... (answered by josgarithmetic)
if it takes 8 men 9 days to dig a tunnel how long will it take 6 men to dig the same... (answered by ikleyn)