Question 182471: It takes nine days for 8 worker to pave a stretch of road. If each worker works at the same rate as each of the others, how long will it take twelve workers to pave the same stretch of road?
Answer by Mathtut(3670) (Show Source): You can put this solution on YOUR website!
8*9=12x........x is number of days
:
12x=72
:
days
RELATED QUESTIONS
When working together worker A and worker B take 8 hours to complete a project.Today they (answered by ankor@dixie-net.com)
Looking for the most efficient method.
20 workers completed a quarter of a job in 8... (answered by majo89)
5 Workers can build a road in 20 days. suppose every worker works at the same rate. if... (answered by ankor@dixie-net.com)
Worker A and worker B, working together, can finish a job in 12 days. After 8 days worker (answered by josmiceli)
A group of 3 workers need 20 days to do a certain job. How long would it take a group of (answered by josgarithmetic)
A group of 3 workers need 20 days to do a certain job. How long would it take a group of... (answered by josgarithmetic)
It takes 4 workers 9 days to lay a stretch of road. How long does it take 6 workers to... (answered by josmiceli)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
It takes worker A six days longer as it takes worker B to finish a certain job. Working... (answered by greenestamps,ikleyn)