SOLUTION: A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days. Working together, how many days can all of them finish the work?

Algebra.Com
Question 167380: A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days. Working together, how many days can all of them finish the work?
Found 2 solutions by ptaylor, Edwin Parker:
Answer by ptaylor(2198)   (Show Source): You can put this solution on YOUR website!
A&B work at the rate of 1/42 job per day
B&C work at the rate of 1/31 job per day
A&C work at the rate of 1/20 job per day
Let t=time it takes all workers, working together, to do the job
Let 1/A=rate at which A works
1/B=rate that B works
1/C=rate that C works
Now we know that:
1/A + 1/B=1/42-------------------eq1
1/B + 1/C=1/31---------------------eq2
1/A + 1/C=1/20---------------------eq3
subtract eq3 from eq1:
1/B - 1/C=1/42 - 1/20------------------eq3a
add eq3a and eq2:
2/B=1/42 - 1/20 + 1/31 (13020 is LCM)
2/B=(310-651+420)/13020=79/13020
1/B=79/26040 job per day-------------------------rate at which B works
substitute the value for 1/B into eq1:
1/A + 79/26040=1/42
1/A=1/42 - 79/26040=(620-79)/26040=541/26040 job per day----rate at which A works
substitute the value for 1/A into eq3:
541/26040 + 1/C=1/20
1/C = 1/20 - 541/26040=(1302-541)/26040=761/26040 job per day----rate at which C works
Together, A, B, & C work at the the rate of:
541/26040 +79/26040 + 761/26040= 1381/26040 job per day
Now, our final equation to solve is:
(1381/26040)t=1 (1 job that is) multiply each side by 26040
(rate at which they work * time it take to complete the job=1 job)
1381t=26040 divide by 1381
t= 18.86 days----------------time it takes all the workers working together
CK
A: (541/26040)*18.86=0.3917 of the job
B: (79/26040)*18.86=0.0572 of the job
C: (761/26040)*18.86=0.5512 of the job
0.3917 + 0.0572 + 0.5512=1.000069
1~~~1
Hope this helps---sorry about the first effort----ptaylor

Answer by Edwin Parker(36)   (Show Source): You can put this solution on YOUR website!
A and B can do a piece of work in 42 days, B and C in 31 days and C and A in 20 days. In how many days can all of them do the work together?

A and B can do a piece of work in 42 days,
So A's and B's combined rate is 1 job per 42 days or  or 

B and C in 31 days
So B's and C's combined rate is 1 job per 31 days or  or 

C and A in 20 days
So C's and A's combined rate is 1 job per 31 days or  or 

Suppose A's rate working alone is is 1 job per x days or  or .

Suppose B's rate working alone is is 1 job per y days or  or .

Suppose C's rate working alone is is 1 job per z days or  or .

Suppose their combined rate is 1 job per d days or  or .


The four equations come from:

       +  = 

             +  = 

       +  = 

             +  = 

       +  = 

             +  = 



       +  +  = 

             +  +  = 

 +  = 
 +  = 
 +  = 
 +  +  = 

Now we must find their combined rate which is

So we line up the first three equations like this and add them all:

           +          = 
               +      = 
               +      = 
         ---------------------
           +  +      = 

           +  +      = 

Dividing both side by 2

           +  +      = 

And since the fourth equation is

           +  +  = 

Since things equal to the same thing are equal to each other,

            = 

Cross-multiplying:

       1381d = 26040
           d = 
           d = 18.85590152 days

Edwin


RELATED QUESTIONS

A and B can do a piece of work in 42 days, B and C in 31 days and C and A in 20 days. In... (answered by Edwin McCravy,AnlytcPhil,Edwin Parker)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)
A,B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in 20 (answered by dkppathak)
A,B and C do a piece of work in 10 days. A and B can do it in 12 days. A and C in 20... (answered by savvyhush23)