SOLUTION: if it takes Jerry 5 weeks to complete a job and Sam 3 weeks, if they work together how long will it take
Algebra.Com
Question 160575: if it takes Jerry 5 weeks to complete a job and Sam 3 weeks, if they work together how long will it take
Answer by ptaylor(2198) (Show Source): You can put this solution on YOUR website!
Let x=amount of time it takes to do the job when they work together
Jerry works at the rate of 1/5 of the job per week
Sam works at the rate of 1/3 of the job per week
Together they work at the rate of:
1/5 + 1/3=3/15 +5/15=8/15 of the job per week
So, our equation to solve is:
(8/15)x=1 (1 job, that is) multiply each side by 15
8x=15 divide each side by 8
x=1.875 weeks---------------------------ans
Another way:
if x=amount of time it takes to do the job when they work together, then, together, they work at the rate of 1/x job per week, so:
1/5 + 1/3 =1/x multiply each term by 15x
3x+5x+15
8x=15----same as before
CK
Amount of work that Jerry does in 1.875 weeks plus the amount of work that Sam does in 1.875 weeks has to equal 1 job completed,so:
(1/5)*1.875 + (1/3)*1.875=1
0.375+0.625=1
1=1
Hope this helps---ptaylor
RELATED QUESTIONS
Jerry and Sam are laying a hardwood floor. Working alone, Jerry can do the job in 20... (answered by josmiceli)
Jake can complete a job in 5 hours while Jerry can complete the same job in 3 hours. How... (answered by solver91311)
If a project takes 2.5 resources 71 weeks to complete and 3.5 resources 46 weeks to... (answered by stanbon)
If it takes Jerry 30 hours to build a shed in the back yard and Tom 15 hours. How long... (answered by math_helper)
if sam can do a certian job in 3 days while it takes fred 6 days to do the same job how... (answered by solver91311)
Adam takes 4 hours to do a job and Sloan takes 5 hours to do the same job. If they work... (answered by lynnlo)
Three workers can complete a job in 3 hours, 5 hours, and 6 hours, respectively. How... (answered by Earlsdon)
Jake can complete a job in 5 hours while Jerry can complete the same job in 3 hours.
a)... (answered by stanbon)
2. Renan can finish a project in 3 weeks. James takes 6 weeks doing the same project. If... (answered by richwmiller)