Question 137212: Arlene and AJ are chemists. AJ can do an emulsion polymerization in 10 hours. If AJ and Arlene work together they can do the experiment in 13 hours. How long will it take Arlene working by herself to do the experiment.
AJ= 10
Arlene= x+10
I think the answer is 3 but that's too obvious.
Answer by checkley77(12844) (Show Source): You can put this solution on YOUR website!
SOMETHING IS WRONG WITH THIS PROBLEM.
IF AJ CAN DO THE EXPERIMENT IN 10 HOURS THEN WITH ARLENE'S HELP THE TIME MUST BE LESS THAN 10. 13 DOES NOT MEET THE TEST.
-------------------------------------------------
ABSOLUTELY THE COMBINED TIME HAS TO BE LESS THAN THE 2 SEPARATE TIMES.
RELATED QUESTIONS
Arlene and AJ are Chemist. AJ can do an emulsion polymerization experiment in 10 hours. (answered by buz_master)
Arlene and AJ are Chemist. AJ can do an emulsion polymerization experiment in 10 hours. (answered by ankor@dixie-net.com)
Aly can paint a room two hours less than AJ. If they will work together, they can finish... (answered by josgarithmetic)
1. Arlene and Lito are travelling north in separate cars on the same highway. Arlene is... (answered by Boreal)
One roofing crew can finish a 2,800-square-foot roof in 12 hours, and another crew can do (answered by josgarithmetic)
John can do a job in 4 hours and Mark can do the same job in 2 hours. If they work... (answered by Cromlix)
Mary and Carol are doing a month project. Carol can do work twice as fast as Mary. If... (answered by josmiceli)
AZra can do a job in 4 hoursthat halycycon can do in 3 hours and silfer can do in 2... (answered by ikleyn)
Arpit can fence a garden in 3 hours, Ankur can do it in 5 hours and Aakash takes 6 hours... (answered by ptaylor)