SOLUTION: If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Algebra.Com
Question 126538: If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
If 6 men can do the job in 14 days, it will take 1 man 6 times as long
so. 1 man will take days
You can read this as: what part of the job can be done by 1 man in 21 days
if 1 man can do 1 job in 84 days
So, 1 man can do 1/4 of the job in 21 days
And 4 men can do 4 times as much, or 1 job, done in the same amount tof time
It takes 4 men to do the job in 21 days
RELATED QUESTIONS
If 6 men can do a piece of work in 14 days, how many men are needed to do the same work... (answered by tutorcecilia,ptaylor)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in... (answered by stanbon)
if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by JimboP1977)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by flame8855,Alan3354)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by solver91311)
If 6 men can do a piece of work in 14 days, how many men are needed to do work in 21... (answered by scott8148,RAY100)
If 6 men can do a piece of work in 4 days, how many men are needed to do the work in 21... (answered by ankor@dixie-net.com)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by babynarah2007)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by John10)