I think this type problem should be considered as a problem in VARIATION.
Common sense tells us that:
Time (t) increases as the amount of job-doing (j) increases.
Time (t) decreases as the number of workers (w) increases.
Therefore, time (t) varies directly as the amount of job-doing (j) and
inversely as the number of workers (w). That is:
-----------------------------------------
A certain job [THAT'S 1 JOB] can be done by 72 men in 100 days.
Solve for k
So
There were 80 men at the start of the project
but after 40 days,....So for those first 40 days,
So the amount of job-doing during those first 40 days was 4/9ths of a job.
So that means there is still 5/9 of a job left to be done.
.....30 of them had to be transferred to another project.So the amount of job-doing left for the remaining 50 men to do was 5/9 of a job.
Answer: 80 days.
Edwin