please help me to answer this question. eight men lake 12 days to cultivate a piece of land.
after working for 3 days. six more men were employed. how long did they take to cultivate a land
~~~~~~~~~~~~~~~~~~
After 3 days, 1/4 of the job was done; 3/4 of the job remained.
8 workers would complete the remaining job in 9 days (under regular conditions).
But 8+6 = 14 workers will complete the remaining job in
= = = = 5 days. ANSWER
Solved.
Usually, in such problems, the problem composers match numbers in a way to get an integer answer.
Then the students are inspired by the beauty of a solution.
They will love Math.
Other " math composers " do not care about it.
Then the students consider such problems as idiotic, and they are right.
These students will hate Math.
Such math composers (of the second kind) should simply ruthlessly be kicked out of the profession
(using the method of " iron broom "), since their activity IS OPPOSITE to goals of education.
-------------------
The solution by @josgarithmetic, giving the answer 9/7 of a day, is INCORRECT.
Simply ignore his post.