SOLUTION: When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 26 days by 23 workers. How many days wou
Algebra.Com
Question 1200680: When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 26 days by 23 workers. How many days would it take to build a similar house with 46 workers?
Answer by Alan3354(69443) (Show Source): You can put this solution on YOUR website!
When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 26 days by 23 workers. How many days would it take to build a similar house with 46 workers?
---------------
Twice the # of workers ---> 1/2 the time.
RELATED QUESTIONS
When building a house, the number of days required to build is inversely proportional to... (answered by ankor@dixie-net.com)
The time is takes to build a skyscraper is proportional to its height and inversely... (answered by josgarithmetic,greenestamps)
The amount of time taken to build a house is inversely proportional to the
number of... (answered by Alan3354)
The number of days required to build a bridge is varies inversely to the number of... (answered by josmiceli)
The number of days it takes to build a house is inversely proportional to the number of... (answered by ikleyn)
The number o days it takes to build a house is inversely proportional to the number of... (answered by josgarithmetic)
Hi. I don't understand how I'm supposed to solve this problem. Could you please clearly... (answered by josgarithmetic)
The time to complete a building project is inversely proportional to the number of people (answered by mananth)
the time(T) required to build a house is inversrly proportionnal to the number of... (answered by stanbon)