Worker A can finish the job in 5 hrs, Worker B in 6 hrs.
If they split the work in half and worker A starts the work, how long will it take to finish the job?
~~~~~~~~~~~~~~~~~~
The problem says that they split the work in half.
As I understand these words, it means that A makes one half of the job, and B makes the remaining half.
Then A will complete his half in 5/2 = 2.5 hours; B will complete his half of the job in 6/2 = 3 hours.
If B works after A (in this case they DO NOT work simultaneously),
then the gob will be complete in 2.5 + 3 hours = 5.5 hours.
If, in opposite, they start simultaneously, then the entire job will be
complete when B will complete his part, i.e. in 3 hours.
Solved.
As I interpret this problem, it is NOT classic joint work problem - - - they are worded differently.
It is different kind of problems.