SOLUTION: Jose can do a certain job in 10 days, and Roy can do the same job in 12 days. If two men work together, how many days would it takes to finish the job?

Algebra.Com
Question 1186458: Jose can do a certain job in 10 days, and Roy can do the same job in 12 days. If two men work together, how many days would it takes to finish the job?
Found 3 solutions by ikleyn, Alan3354, greenestamps:
Answer by ikleyn(52776)   (Show Source): You can put this solution on YOUR website!
.
Jose can do a certain job in 10 days, and Roy can do the same job in 12 days.
If two men work together, how many days would it takes to finish the job?
~~~~~~~~~~~~~~~

Jose makes   of the job per day.


Roy makes    of the job per day.


Working together, they make   =  =   od the day.


It means that wotking together they will complete the job in   = 5   days.    ANSWER

Solved.

-----------------

It is a standard and typical joint work problem.

There is a wide variety of similar solved joint-work problems with detailed explanations in this site.  See the lessons
    - Using Fractions to solve word problems on joint work
    - Solving more complicated word problems on joint work
    - Selected joint-work word problems from the archive


Read them and get be trained in solving joint-work problems.

Also,  you have this free of charge online textbook in ALGEBRA-I in this site
    - ALGEBRA-I - YOUR ONLINE TEXTBOOK.

The referred lessons are the part of this textbook under the topic
"Rate of work and joint work problems"  of the section  "Word problems".


Save the link to this online textbook together with its description

Free of charge online textbook in ALGEBRA-I
https://www.algebra.com/algebra/homework/quadratic/lessons/ALGEBRA-I-YOUR-ONLINE-TEXTBOOK.lesson

to your archive and use it when it is needed.



Answer by Alan3354(69443)   (Show Source): You can put this solution on YOUR website!
Jose can do a certain job in 10 days, and Roy can do the same job in 12 days. If two men work together, how many days would it takes to finish the job?
----------
10*12/(10+12) = 120/22
= 60/11 days.

Answer by greenestamps(13198)   (Show Source): You can put this solution on YOUR website!


This kind of "working together" problem is so common that it is worthwhile to remember the simple formula shown by one of the tutors.

If you want to understand the standard formal algebraic method for solving the problem (which leads to that formula), use the method shown by the other tutor.

And for another method for solving this type of problem that many students prefer, you can try this:

Consider the least common multiple of the two given times of 10 days and 12 days, which is 60 days.
In 60 days, Jose could do 60/10=6 of these jobs and Roy could do 60/12=5 of them.
So together in 60 days the two of them could do 11 of the jobs.
And so the amount of time it would take the two of them together to do the one job is 60/11 days.


RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
mr a can do a job for 3 days while mr b can do the same job for 6 days. if the two of... (answered by stanbon)
Hi 10 men and 20 women can do a job in 15 days. 15 men and 10 women can do the same job... (answered by VFBundy)
3 men can do the job of 4 women. If 3 men can do a job in 8 days, in how many days can 5... (answered by richwmiller)
Two men working together can do a job in 20 days. After both have been working 10 days,... (answered by scott8148)
if 3 men can repair the house in 20 days,how many days can 5 men do the same... (answered by ankor@dixie-net.com)
One person can do a certain job in six days, a second person can do the same job in two... (answered by mananth)
Ali can do a certain job in 12 days,Baisi can do it in 15 days while Charles in 20... (answered by ankor@dixie-net.com)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)