The local post office has three machines for sorting the mail. If each works alone, machine A can accomplish the job in 2 hours, machine B in 3hours and machine C in 1 1/2 hours. Machine C begins the job and works for half an hour when it suddenly breaks down. Machine A and B are then activated and work together to complete the sorting process. How long does it take for machines A and B to finish.
Machine A does job in 2 hours, or of job in 1 hour
Machine B does job in 3 hours, or of job in 1 hour
Machine C does job in hours, or of job in 1 hour
With machine C working for hour, and with T being the time machines A & B take to finish the job, we get:
2 + 3T + 2T = 6 ------- Multiplying by LCD, 6
3T + 2T = 6 - 2
5T = 4
Time machines A and B took to complete job, or