Make the following chart. Fill in the times, letting the time that
only Mark and Bren worked together after Lex quit be t. When they
did the whole job themselves we put 1 for the part of a job done, which
means 100% of the job was done.
| Part of | Rate | Time |
| job | in | taken |
| done | jobs/hr | in hrs |
------------------------------------
Mark | 1 (all)| | 12 |
Lex | 1 | | 16 |
Bren | 1 | | 19 |
------------------------------------
Mark | | | 4 |
Lex | | | 4 |
Mark | | | t |
Bren | | | t |
First we use the top three to get expressions for their rates
by dividing the part of job done (1) by the time.
| Part of | Rate | Time |
| job | in | taken |
| done | jobs/hr | in hrs |
------------------------------------
Mark | 1 (all)| 1/12 | 12 |
Lex | 1 | 1/16 | 16 |
Bren | 1 | 1/19 | 19 |
------------------------------------
Mark | | 1/12 | 4 |
Lex | | 1/16 | 4 |
Mark | | 1/12 | t |
Bren | | 1/19 | t |
Next we multiply the the rates by the time to get the
parts of a job done.
| Part of | Rate | Time |
| job | in | taken |
| done | jobs/hr | in hrs |
------------------------------------
Mark | 1 (all)| 1/12 | 12 |
Lex | 1 | 1/16 | 16 |
Bren | 1 | 1/19 | 19 |
------------------------------------
Mark | 4/12 | 1/12 | 4 |
Lex | 4/16 | 1/16 | 4 |
Mark | t/12 | 1/12 | t |
Bren | t/19 | 1/19 | t |
Those four parts of a job below the second dotted line must
add to be 1 job.
Reduce the fractions that will reduce:
Multiply through by LCD of 228
That's the number of hours he worked with Bren.
The total time Mark worked was the 4 hours he worked with Lex only
plus the 3.064516129 hours he worked with Bren only after Lex quit
or
7.064516129 hours. <--answer
Edwin