It can be solved mentally, without using equations. The new pump works as productive as two old pumps. So, the old pump and the new pump, working together, are equivalent to three old pumps. One old pumps completes the job in 12 hours. Hence, the two pumps, been equivalent to 3 old pumps, will complete the job in 12/3 = 4 hours. ANSWER