Question 1145987: Matthew can finish a work in 6 days, Martin in 8 days and Raymund also in 8 days. How long will it take the three gentlemen to finish the same work together?

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
x/6+x/8+x/8=1
x/6+2x/8=1
x/6+x/4=1
2x/12+3x/12=1
5x/12=1
5x=12
x=12/5
x=2.4 days
check
2.4/6+2.4/8+2.4/8=1
1=1
ok


RELATED QUESTIONS

john can finish a piece of work in 6 days, martin in 8 days and raymund also in 8 days.... (answered by josgarithmetic)
john can finish a piece of work in 6 days, martin in 8 days and raymund also in 8 days.... (answered by josgarithmetic)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
Mr. Mann can lay a walk in 6 days, and Mr. Gregory in 8 days. How long will it take Mr.... (answered by TimothyLamb,MathTherapy)
Snowhite Paint Co. contracts to paint three houses. Andy can paint a house in 6 days,... (answered by richwmiller)
if 4 men can finish a work in 5 days, how long will it take 8 men to do the same... (answered by ewatrrr)
A, B and C can finish a job in 6 days. If B and C work together, the job will take 9... (answered by josmiceli)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)