Question 1145880: A worker can clean a pool in 4hours less time than it takes another. if the men work together the job takes 2⅔hours. how long will it take each man to work alone.
Answer by josgarithmetic(39620)   (Show Source): You can put this solution on YOUR website!

-







Slow worker, 8 hours alone
Fast worker, 4 hours alone

RELATED QUESTIONS

2 landscape workers can complete a certain job in a total of 20 hours. Working alone,... (answered by josgarithmetic)
Two landscape workers can complete a certain landscaping job in a total of 20 hours.... (answered by richwmiller)
joann can clean all the snow from a strip of driveway in 4 hours less time than it takes... (answered by richwmiller)
A 3-men crew can do a certain job in 4 hours, while it takes a 4-men crew to do the same... (answered by ankor@dixie-net.com)
It takes one worker 5 hours to do the same job that it takes another worker 3 hours to... (answered by ankor@dixie-net.com)
One worker can clean a warehouse in 10 hours. Another worker can clean the same... (answered by ewatrrr)
it takes mary 3 hours more to do a job than it takes jane. if they work together,they can (answered by josmiceli)
it takes mary 3 hours to do a job that it takes jane. If they work together, they can... (answered by richwmiller)
Working together, Sarah and Heidi can clean the garage in 6 hours. If they work alone, it (answered by richwmiller)