SOLUTION: 8 labourers cut a field in 6 days. (a) how many men will cut the field in 3 days? (b) how long will it take 12 men cut the field? (c) how long will it take 10 men to cut the fie

Algebra.Com
Question 1142410: 8 labourers cut a field in 6 days.
(a) how many men will cut the field in 3 days?
(b) how long will it take 12 men cut the field?
(c) how long will it take 10 men to cut the field?
(d) how long will it take 20 labourers cut the field?

Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39630)   (Show Source): You can put this solution on YOUR website!
"Cut a field" is one entire job.

n, number of laborers
R, rate of one single laborer
x, amount of time
j, amount of jobs (being 1 for the example problem)
-



------------------------------------
8 laborers cut a field in 6 days.
------------------------------------


--------the one-laborer work rate in FIELDS per DAYS

You can solve each of a, b, c, and d using this.

Answer by ikleyn(52903)   (Show Source): You can put this solution on YOUR website!
.

            I edited the post,  replacing  "cut the field"  by  "plow the field"  and  "labourers"  by  "laborers"  everywhere.


8 laborers plow a field in 6 days.
(a) how many men will plow the field in 3 days?
(b) how long will it take 12 men plow the field?
(c) how long will it take 10 men to plow the field?
(d) how long will it take 20 laborers plow the field?
~~~~~~~~~~~~~~~~~


Solution

            There are two  ( or three :) )  standard ways to solve problems like these and to explain the solution.

First way

(a)  The entire work requires  8*6 = 48 labor-days.


     To find how many laborers "x" are needed to complete the job in 3 days, write an equation

         48 = 3x,      (1)

     which immediately gives the solution and the answer

         x = 48/3 = 16 days.


Second way

(a)  The rate of work of each laborer is   of the entire job per day in the first case.


     In the second case, the rate of work of each laborer is    of the job per day


     Assuming that the rate of work is the same in both cases, you get an equation

          = .


     From the equation, you get 

          8*6 = 3x       ( ! same equation as (1) (!) ),   so

           x  =  = 16.


      You get the same answer.


Third way

      When you solve such problems several times, you will find it OBVIOUS that two times shorter time period requires two times larger team.


Armed with this knowledge,  you can easily solve the rest of problems by any of these three ways  ON  YOUR  OWN.



RELATED QUESTIONS

IF 10 MEN CAN CUT A PIECE OF WOOD IN 4 DAYS,HOW LONG WILL IT TAKE 8 MEN TO CUT THE SAME... (answered by ramkikk66)
If 2 men take 8 days to mow a field and the faster man can do it alone in 12 days how... (answered by ankor@dixie-net.com)
If 8 men could plough a field in 9 days, how many days would it take 18 men working at... (answered by neatmath)
HOW MANY MEN WILL IT TAKE TO CUT AN AREA OF GRASS 20 FEET BY 20000 FEET IN THREE DAYS (answered by richwmiller)
If 15 men , woking 9 hours a day, can reap a field in 16 days , in how many days will 18... (answered by ankor@dixie-net.com)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
If 12 men mow a field of 40 acres in 8 days working 10 hours a day how many days will it... (answered by ankor@dixie-net.com,stanbon)
4 men can build a shed in 12 days. How many men will it take to build the same shed in 3 (answered by josmiceli)
If it took 8 labourers 28 days to dig a trench,how long will it take 6 labourers working... (answered by stanbon,Edwin McCravy)