SOLUTION: Ben finish a job 2 hours longer than Daniel. After Ben had been working for 1 hour Daniel joined him and they completed the remaining portion of the job for 3 hours. How long would

Algebra.Com
Question 1122892: Ben finish a job 2 hours longer than Daniel. After Ben had been working for 1 hour Daniel joined him and they completed the remaining portion of the job for 3 hours. How long would it take Ben to do the job?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Ben finish a job 2 hours longer than Daniel.
After Ben had been working for 1 hour Daniel joined him and they completed the remaining portion of the job for 3 hours.
How long would it take Ben to do the job?
:
d = time required by Daniel to complete the job
"Ben finish a job 2 hours longer than Daniel."
(d+2) = time required by Ben
Let the completed job = 1
:
After Ben had been working for 1 hour Daniel joined him and they completed the remaining portion of the job for 3 hours. "
Ben worked 4 hrs, Daniel worked 3 hrs
:
A shared work equation
+ = 1
multiply equation by d(d+2)
4d + 3(d+2) = d(d+2)
4d + 3d + 6 = d^2 + 2d
7d + 6 = d^2 + 2d
form a quadratic equation on the right
0 = d^2 + 2d - 7d - 6
d^2 - 5d - 6 = 0
Factors to
(d-6)(d+1) = 0
the positive solution
d = 6 hrs Daniel working time alone
and obviously
8 hrs Ben working alone
:
;
check
+ = 1

RELATED QUESTIONS

Mario can finish a job for 2 hours longer than karlo. After mario had been working for 1... (answered by josgarithmetic)
A painter can finish a painting job 2 hours longer than his fellow-painter. After... (answered by jorel1380)
Daniel and Lauren are painters. Daniel is faster than Lauren by 2 hours. Occasionally... (answered by Edwin McCravy)
Ben and Jerry want to make some ice cream. Ben can pick the strawberry field by himself (answered by richwmiller)
Ben and Jerry want to make some ice cream. Ben can pick the strawberry field by himself... (answered by richwmiller)
Hi Ali had 60% of the total number of marbles his other 3 friends had. Cindy had 50% of (answered by josgarithmetic,ikleyn,MathTherapy)
John can finish a job two hours longer than Cris. after working for one hour,Cris joins... (answered by josgarithmetic)
An apprentice carpenter can complete a job in 8 hours. After he has been working on the... (answered by lwsshak3)
A woman can do a certain job in 5 hours. Her daughter can do it in 7 hours. After the... (answered by josgarithmetic)