Answer by ikleyn(52779)   (Show Source): You can put this solution on YOUR website!
.
The master makes    of the job per hour.


The partner makes    of the job per hour.


Working together, they make   =  =   of the job per hour.


Hence, it will take them   =  hours = 8 hours and 35 minutes (approximately) to complete the job working together.

Solved.

-------------------
It is a typical and standard joint work problem.

There is a wide variety of similar solved joint-work problems with detailed explanations in this site.  See the lessons
    - Using Fractions to solve word problems on joint work
    - Solving more complicated word problems on joint work
    - Selected joint-work word problems from the archive


Read them and get be trained in solving joint-work problems.

Also,  you have this free of charge online textbook in ALGEBRA-I in this site
    - ALGEBRA-I - YOUR ONLINE TEXTBOOK.

The referred lessons are the part of this textbook under the topic
"Rate of work and joint work problems"  of the section  "Word problems".


Save the link to this online textbook together with its description

Free of charge online textbook in ALGEBRA-I
https://www.algebra.com/algebra/homework/quadratic/lessons/ALGEBRA-I-YOUR-ONLINE-TEXTBOOK.lesson

to your archive and use it when it is needed.


RELATED QUESTIONS

Art can paint a set of kitchen cabinets in 3 hours. His father can do it in 1 hour. How... (answered by bostonmathtutor)
Dave can build a set of cabinets in 5 hours. It would take Alan twice as long as Eric to... (answered by solver91311,lwsshak3)
This one is set up like a word problem and I could use some assistance. A company... (answered by ankor@dixie-net.com)
A cabinet maker builds 3 cabinets in 2 days. An apprecntice workes 1/2 as fast. How many... (answered by josmiceli)
Dave builds a set of cabinets in 5 hours. It would take Alan twice as long as Eric to... (answered by solver91311)
Janet can paint a kitchen in 3 hours and Charles can paint the same kitchen in 5 hours .... (answered by Alan3354)
Please help. The demand for cabinets depends on the price per cabinet. A manufacturer... (answered by solver91311)
A painter can paint a kitchen in 15 hours. An apprentice can paint the same kitchen in 30 (answered by Cromlix)
A furniture shop refinishes cabinets. Employees use one of two methods to refinish each... (answered by mananth)