SOLUTION: 4 skilled workers can do a job in 5 days, 5 semi-skilled workers can do the same job in 6 days. How long does it take 1 semi-skilled and 2 skilled workers to do the job working tog

Algebra.Com
Question 1110376: 4 skilled workers can do a job in 5 days, 5 semi-skilled workers can do the same job in 6 days. How long does it take 1 semi-skilled and 2 skilled workers to do the job working together?

I think you do 5/4 and 5/6, and then you add 5/6+5/6+5/4. I'm not sure though.

Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
4 skilled workers rate, , ----rate for 1 skilled worker

5 semi-skilled workers, , ----rate for 1 semi-skilled worker

How long for 1 semi-skilled and 2 skilled workers working together?
Their collective work rate is






----------JOBS per DAYS

In DAYS per 1 JOB, this is days.

RELATED QUESTIONS

4 skilled workers can do a job in 5 days. 5 semi skilled worers can do The same job in... (answered by josgarithmetic)
Working together, 4 skilled workers can complete a job in 5 days. However, 5 semi-skilled (answered by ankor@dixie-net.com)
4 skilled workers can complete a job in 5 days. 5 semi-skilled workers can complete the... (answered by josgarithmetic,ikleyn)
If 25 skilled men can complete a job in 8 days; 12 skilled men and 15 unskilled men can... (answered by macston,MathTherapy)
If M workers can do a job in D days, how long would it take 40 workers to do the same... (answered by ptaylor)
if 5 men (assume equally skilled) using 2 machines can complete a job in 7 days. 1. how... (answered by richwmiller)
A boys' club decides to build a cabin. The job can be done by 3 skilled workmen in 4 days (answered by stanbon)
3 workers can do a job in 36 days. How long would it take 2 workers to finish the same... (answered by macston,Edwin McCravy)
If 4 workers do a job in 6 days..How long will 24 workers will need do the... (answered by josgarithmetic)