Question 1107182: A farmer has 10men to finish a piece of work on his farm for 4 days .how long will it take 4men to finish the same work at the same rate
Answer by ikleyn(52914)   (Show Source): You can put this solution on YOUR website!
.
It will take   = 2.5 times as long:  4*2.5 = 10 days.


RELATED QUESTIONS

if it takes 10men 20 seconds to finish a piece of work,how many seconds will it take 2... (answered by Alan3354)
john can finish a piece of work in 6 days, martin in 8 days and raymund also in 8 days.... (answered by josgarithmetic)
john can finish a piece of work in 6 days, martin in 8 days and raymund also in 8 days.... (answered by josgarithmetic)
If eight men can finish work on a piece of land for four hours, how long will it take... (answered by richwmiller)
Joshua can finish a certain job in 4 days while Kevin can finish the same job in 2 days.... (answered by stanbon)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days. They work... (answered by richwmiller)
if 4 men can finish a work in 5 days, how long will it take 8 men to do the same... (answered by ewatrrr)
Two printers working together can finish a piece of work in 6 days. Working alone, one of (answered by josmiceli)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)