Question 1093328: Mark can finish a task alone in 24 days while Andres can do the same task in 18 days. If they work together, how long can they finish the task?

Answer by ikleyn(52814)   (Show Source): You can put this solution on YOUR website!
.
Mark makes  of the work per day. It is his rate of work.

Andres makes  of the work per day. It is his rate of work.

Working together, they make  =  =  of the work per day.


Hence, it will take  =  days for them to complete the job working together.


----------------
It is a typical joint work problem.

There is a wide variety of similar solved joint-work problems with detailed explanations in this site.  See the lessons
    - Using Fractions to solve word problems on joint work
    - Solving more complicated word problems on joint work
    - Selected joint-work word problems from the archive


Read them and get be trained in solving joint-work problems.

Also,  you have this free of charge online textbook in ALGEBRA-I in this site
    - ALGEBRA-I - YOUR ONLINE TEXTBOOK.

The referred lessons are the part of this textbook under the topic
"Rate of work and joint work problems"  of the section  "Word problems".


Save the link to this online textbook together with its description

Free of charge online textbook in ALGEBRA-I
https://www.algebra.com/algebra/homework/quadratic/lessons/ALGEBRA-I-YOUR-ONLINE-TEXTBOOK.lesson

to your archive and use it when it is needed.



RELATED QUESTIONS

Mark can finish a task alone in 24 days while Andres can do the same task in 18 days. If (answered by solver91311)
jake can do a certain task in 10 days . after he has worked for 2 days ,tom comes to help (answered by josgarithmetic)
Larry can do a certain task 6h longer than rhea. if they work together, they can finish... (answered by josgarithmetic)
John can complete a task in 18 days while Peter can complete it in 12 days. How many days (answered by math_helper)
Working alone, A can complete a task in ‘a’ days and B in ‘b’ days. They take... (answered by ikleyn)
P can complete a task in x days while Q takes (x + 12) days to do the same task. a) What (answered by Edwin McCravy,Theo)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
Julia and Robert can finish a piece of work in 15 days. Julia can do the job alone in 20... (answered by stanbon,ewatrrr,richwmiller)
joe can do a job in 3 days, while jill can do the same job in 6 days. How long will they... (answered by ikleyn)