SOLUTION: 4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which 4 men were employed.find the total number of days taken to complete the work?

Algebra.Com
Question 1086672: 4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which 4 men were employed.find the total number of days taken to complete the work?
Found 2 solutions by josmiceli, MathTherapy:
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
4 men planned to complete a piece of work in 10 days
1 man will take 4 times as long to do the work
The rate for 1 man is [ 1 job ] / [ 40 days ]
-----------------------------------------------
In 4 days 1 man does of the job
In 4 days 3 men do of the job
-----------------------------------------------
There is of the job left to do
Let = time in days for 4 men to do
of the job
One of the men will take 4 times as long to do
of the job, so is the rate for 1 man
-----------------
The rate for 1 man is [ 1 job ] / [ 40 days ], so I can say:



days
--------------------
The total nuber of days to complete the work is:
days
--------------------
Definitely get a 2nd opinion on this. I could easily
go off track on this.

Answer by MathTherapy(10552)   (Show Source): You can put this solution on YOUR website!
4 men planned to complete a piece of work in 10 days,3 men worked for 4 days after which 4 men were employed.find the total number of days taken to complete the work?
It depends!
In 4 days, 3 men completed: of the job, leaving undone.
Now, to complete the remaining of the job, how many men are working? Is it:
1) the original 4, plus the newly-employed 4, for a total of 8?
2) the 3 that worked for 4 days, plus the 4 newly-employed 4, for a total of 7?
3) the 4 newly-employed for a total of 4?
RELATED QUESTIONS

18 men can dig a ditch in 10 days. After they have worked for 4 days how many more men... (answered by ankor@dixie-net.com)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
20 men can do a piece of work in 24 days. After working for few days,4 men are added and... (answered by fractalier)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
10 men can do a piece of work in 24 days. After working 6 days,few men were added to... (answered by Edwin McCravy)
20 men can do a piece of work in 24 days. After working for 6 days, additional number of... (answered by richwmiller)
6 men take 4 days to complete a part of a job. how many days will it take 8 men to do the (answered by ankor@dixie-net.com)
A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were... (answered by josgarithmetic)
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to... (answered by josmiceli)