Question 1082143: 28 peons can finish the job in 60 days,. At the start of 16th day 5 peons were laid off and after the 45th days, 10 more peons were hired. How many days they were delayed finishing the job?
Answer by jorel1380(3719) (Show Source): You can put this solution on YOUR website!
28 peons x 60 days=1680 peons in 1 day
28 x 15/1680=1/4 of the work done after 15 days
(46-16) x 23/1680 +420/1680=1110/1680ths of the work done
1680-1110=570/1680 of the work left
570/1680 / 33/1680=570/33=17.27 days of work left after the 45th day
45+17.27-60=2.272727 days delayed finishing the job. ☺☺☺☺
RELATED QUESTIONS
80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the... (answered by josmiceli,Theo)
twelve men can finish the job in 20 days. Five men were working at the start and after 10 (answered by lwsshak3)
Twenty men can finish the job in 20 days. Twenty men were hired at the start and 10 quit... (answered by richwmiller)
Twenty men can finish the job in 30 days. Twenty five men were hired at the start and 10... (answered by josgarithmetic)
Twelve men can finish a job in 16 days. Five men were working at the start, after 8 days... (answered by ankor@dixie-net.com,josgarithmetic)
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to... (answered by 12217B)
A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A (answered by htmentor)
A certain job can be done by 72 men in 100 days. There were 80 men at the start of the... (answered by jorel1380)
20 artisans can accomplish a job in 30 straight days, 25 artisans were hired at the... (answered by josgarithmetic)