SOLUTION: Four hundred men could do the job in 10 days. Paul had 600 men on the job for 5 days. How many men did he need for the next 5 days to finish the job on time?

Algebra.Com
Question 1071843: Four hundred men could do the job in 10 days. Paul had 600 men on the job for 5 days. How many men did he need for the next 5 days to finish the job on time?
Answer by addingup(3677)   (Show Source): You can put this solution on YOUR website!
400 in 10 days = 1 man in 4,000 days
600 in 5 days = 1 man in 3,000 - need 1,000 more days and 1,000/5 = 200 men

RELATED QUESTIONS

if 3 men can repair the house in 20 days,how many days can 5 men do the same... (answered by ankor@dixie-net.com)
Sixty-Four men do a job in 15 days. How many more men will it take to do the job in 12... (answered by josgarithmetic,MathTherapy)
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
12 men complete the job in 6 days, 10 men and 21 women complete the same job in 3 days.... (answered by josgarithmetic)
Y men can do a job in 20 days. They work for 8 days and rest for 4 days. For them to... (answered by ankor@dixie-net.com)
3 men can do the job of 4 women. If 3 men can do a job in 8 days, in how many days can 5... (answered by richwmiller)
8 men OR 15 boys can do a job in 20 days. How many days will a group of 4 men and 5 boys... (answered by richwmiller)
10 Men begin to work together on a job, but after some days, 4 of them left the job. As a (answered by josmiceli)
Hi 10 men and 20 women can do a job in 15 days. 15 men and 10 women can do the same job... (answered by VFBundy)