1. "It took two people to complete carpeting in 10 days" ---> it means that the entire job is 2*10 = 20 man-days. 2. To complete it in 4 days,= 5 workers are needed. 3. Since you just have two workers ready, you need 5-2 = 3 additional carpenters. Answer. 3 additional carpenters are needed.