Question 1059172: If 8 men can paint a school in 15 days, how many days would it take for 12 men to paint the same school , assuring that they work on the same rate.
Answer by jorel555(1290) (Show Source): You can put this solution on YOUR website!
If 8 men can paint one school in 15 days, then each man paints 1/8 x 1/15, or 1/120 of a school per day. 12 men working each day means 12/120ths of a school get done per day. It would take these men 120/12, or 10 days to finish the job. ☺☺☺☺
RELATED QUESTIONS
If 8 men paint a school in 15 days, how many days will 12 men take to paint a similar... (answered by josgarithmetic,stanbon)
IT TAKES 20 MEN 60DAYS TO COMPLETE A BUILDING WORK, HOW MANY DAYS LONGER WOULD IT TAKES... (answered by josgarithmetic,Alan3354,greenestamps,MathTherapy)
17 men can paint a wall in 6 days. How long will 2 men take to paint the same... (answered by stanbon)
Al can paint a certain house in 10 days and Ben can paint the house in 12 days. How long... (answered by scott8148)
A can paint a certain house in 10 days and B can paint the same house in 12 days. How... (answered by Alan3354)
Several men can paint a bridge in 15 days
a)how long would it take three men to paint... (answered by josgarithmetic)
Jose can paint a house in 10 days and peter can paint the same house in 12 days . how... (answered by nerdybill)
A contractor estimates that he can paint a house in 5 days by using 6 men. if he actully... (answered by ankor@dixie-net.com)
If 4 men can paint a house in 5 days, in how many days can 10 men paint the same... (answered by Fombitz)