Answer by josgarithmetic(39628) (Show Source): You can put this solution on YOUR website!
a, b, c, the times in days for A, B, and C to do "one whole work". Use the work rates as in unit of .
A sequence of workers has done one whole job.
Goal is to solve for a, b, and c.
Use the first two equations to solve each in terms of b.
-
-
-
Substitute these into the Finished In Thirteen Days equation.
Simplify.
, and simplest denominator IS 2*2*2*2*3*b;
------------Seems strange, maybe correct, but needs to be rechecked ... Maybe a mistake was made. If you can understand the process up to here, your work MIGHT be better and without any mistake I made. You could then continue to go back to the first two equations to solve for a and c.
RELATED QUESTIONS
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
A can do a work in 12 days and B in 18 days. A started the work and B joined him later.... (answered by ankor@dixie-net.com,LinnW)
'A' and 'B' together can complete a work in 3 days. They started together. But after 2... (answered by josgarithmetic)
A can do a work in 12 days ;B in 6 days and C in 3 days.A and B start working together... (answered by Edwin McCravy)
if A , B , and C can work in 10 days
A and C can work in 12 days
A and B can work in... (answered by Edwin McCravy)
A completes one work in20 days. B cmpletes the same work in 25 days while C completes the (answered by ankor@dixie-net.com)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A, B, and C can do a piece of work in 10 days. A and B can do it in 12 days, A and C in... (answered by josmiceli)