Question 1037565: (a).60 people working 8 hours a day takes 4 days to farm . How long will it take 20 people to do the same farm if they work 15 hours a day?Thank you
Answer by ikleyn(52803) (Show Source): You can put this solution on YOUR website!
.
(a).60 people working 8 hours a day takes 4 days to farm . How long will it take 20 people to do the same farm if they work 15 hours a day?Thank you
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
60*8*4 = 20*15*d.
Find d, the number of days under the question, from this equation.
The equation says that the number of man-hours is the same in both cases.
RELATED QUESTIONS
It takes 3 people 20 days to finish a job. How long will it take 4 people working at the (answered by stanbon)
A machine can harvest the farm in 15 days working for 8 hours a day. How long will 2... (answered by ikleyn,greenestamps)
It takes 9 people 9 days to finish a project if they work 9 hours a day. If only 8 people (answered by robertb)
If 10 men working 8 hours a day take 15 days to complete a job.How long will it take 20... (answered by lwsshak3)
Six men working at the same rate can weed a farm in 16 days. After working for 4 days, 2... (answered by mananth,josgarithmetic)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)
It takes 4 people 3 days to dig a small field how long would it take 3 people to do the... (answered by josgarithmetic)
the time t required to do a certain job varies inversely as the number of people in... (answered by ankor@dixie-net.com)
if it takes 7 people 15 days to do a job, how long will it take 3 people to do the same... (answered by ankor@dixie-net.com)