SOLUTION: A and B working together can finish the job in 10 days. if A works 4 days and B works 3 days, one-third of the job shall be finished. how many days will it A to finish the job

Algebra.Com
Question 1037379: A and B working together can finish the job in 10 days. if A works 4 days and B works 3 days, one-third of the job shall be finished. how many days will it A to finish the job
Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39618)   (Show Source): You can put this solution on YOUR website!
Time for them to do one job each, a and b.
Rates together are additive, and each should be done as JOB/TIME.











Isolate either variable in either equation and use for substitution.






















Ignore b=0, and take . Now you can find a for the time A needs to do one whole job.

Return to this one:
which became ;





Now you should be able to setup an equation to help answer the question.
Let A finish the job of doing the unfinished two-thirds of a piece of work.
Let x be the number of days for A to do two-thirds of a piece of work.

Answer by ikleyn(52794)   (Show Source): You can put this solution on YOUR website!
.
A and B working together can finish the job in 10 days.
If A works 4 days and B works 3 days, one-third of the job shall be finished.
How many days will it A to finish the job
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

There is much easier and more straightforward way to solve the problem, if you correctly choose the unknowns.

Let "a" be the rate-of-work of A, and
let "b" be the rate-of-work of B.

Then from the condition you immediately get these two equations for two unknowns

10a + 10b = 1,    (1)
 4a +  3b = .   (2)

Multiply equation (2) by 3 (both sides). Then you can rewrite the system in the form

10a + 10b = 1,    (1')
12a +  9b = 1.    (2')

Now, multiply equation (1') by 6, multiply equation (2') by 5 and distract.
In this way you eliminate "a" and obtain a single equation for "b"

60b - 45b = 5 - 4,   or   15b = 1,   b = .

Then from (1)  10a = 1 - 10b = 1 -  = 1 -  = ,
Hence, a = .
The rate of "a" is  job-per-day; the rate of "b" is  job-per-day.

Answer. A will complete the job in 30 days.  B will complete the job in 15 days.

The lesson to learn from this solution: choose correctly the unknowns when solving rate-of-work and joint-work problems.


RELATED QUESTIONS

A and B working together can finish a job in T days. If A works alone and completes the... (answered by Edwin McCravy,josmiceli)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A and B working together can do a job in 10 days. One takes 5 days less than the other to (answered by vleith)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
if A can do the work in "x" days and B in "y" days, how long will they finish the job... (answered by Theo)
Brain and David can finish the job in 12 days if they work together. If only one of them... (answered by ankor@dixie-net.com)
When A,B and C work together, they can finish installing the garden in 3 days. The job... (answered by ikleyn)
a and b can each do a piece of work in 15 days and 18 days. if a works for 10 days, how... (answered by stanbon)
Please solve this question : two persons A and B together can do work in 10 days. the... (answered by richwmiller)