Question 1036966: If it takes a crew 9 days to do 80% of the job, how many more days will it take to finish the job 100%
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
Their rate of working is:
jobs / days
Divide top and bottom by
jobs / days

The job can be finished in 2.25 days

RELATED QUESTIONS

A painter completes 2/9 of a job in 3 days. At this rate, how many more days will it take (answered by JulietG)
All members of a crew work at the same pace. If only 4 of them are working, they complete (answered by josgarithmetic)
If it takes 4 days for 6 people to finish a job, than how many days does it take 8 people (answered by stanbon)
Peter can do a whole job in half the time it takes Henry to do it. Together they can... (answered by karaoz)
Peter can do a whole job in half the time it takes Henry to do it. Together they can... (answered by josgarithmetic,MathTherapy)
It takes worker A six days longer as it takes worker B to finish a certain job. Working... (answered by greenestamps,ikleyn)
A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take to (answered by TimothyLamb)
One crew can detassel a field of corn in 6 days. Another crew can do the same job in 4... (answered by ankor@dixie-net.com)
If 3 people finish a given job in 8 days,how many days will it take for 2 people to... (answered by ptaylor)