Question 1034509: Can someone please help me solve this work word problem?
Tom and Sam can finish a plowing job in two hours. Tom working alone can do the job in 7 hours. How long would it take Sam to finish the same job alone?
Any help would be appreciated.

Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
Tom and Sam can finish a plowing job in two hours. Tom working alone can do the job in 7 hours. How long would it take Sam to finish the same job alone?
-----
together rate:: 1/2 job/hr
----------------------
Tom's rate:: 1/7 job/hr
Sam's rate:: 1/x job/hr
------------------------------
Equation:
rate + rate = together rate
1/x + 1/7 = 1/2
-------------------------
14 + 2x = 7x
5x = 14
x = 2.8 hrs = 2hr 48 min (time for Sam to do the job alone)
------------
Cheers,
Stan H.

RELATED QUESTIONS

Andrei Toom's word problem from his article... (answered by scott8148)
I have a homework problem that I can't seem to solve. Could someone help me please. thank (answered by stanbon)
please help me to solve this problem. Thanks. If 30 laborers working 7 hours a day can... (answered by josmiceli)
"This is the problem. Would you please help me with this? Thank You!" ---> A and B... (answered by ankor@dixie-net.com)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ptaylor)
If sam can do a job in 4 days that Lisa can do in 6 days, and Tom can do in 2 days, how... (answered by nerdybill)
Please help me solve this word problem thanks! 3 drivers Tom, Zane, and Melissa can... (answered by ikleyn)
I have these questions below that I feel would have the same type of set up, however, I... (answered by oscargut)
if sam can do a job in 4 days that lisa can do in 6 days and tom can do in two days how... (answered by ankor@dixie-net.com)