Question 1028509: It takes 4 workers 42 days to complete a job. If 2 of the workers only work half days, how long will it take them to complete the job?
*I am looking for help on this question, I haven't been able to find any help thus far. My first reaction to this problem was to divide the 42 in half, and then divide one of the halves in half, and add it to the 42 to get the new total, but I don't believe that is right. I was wondering if anyone could show me how to solve this kind of story problem. Thank you.

Found 2 solutions by addingup, ikleyn:
Answer by addingup(3677)   (Show Source): You can put this solution on YOUR website!
4 workers 42 days so the task to be completed, if it was just 1 man, is:
42*4 = 168
Now we have:
4 full time
2 1/2 time = 1 full time
So we have 5 men
168/5= 33.6 days

Answer by ikleyn(52803)   (Show Source): You can put this solution on YOUR website!
.
It takes 4 workers 42 days to complete a job. If 2 of the workers only work half days, how long will it take them to complete the job?
*I am looking for help on this question, I haven't been able to find any help thus far. My first reaction to this problem was to divide the 42 in half, and then divide one of the halves in half, and add it to the 42 to get the new total, but I don't believe that is right. I was wondering if anyone could show me how to solve this kind of story problem. Thank you.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Let me re-formulate the problem as I understand it.

    It takes 4 workers 42 days to complete a job. If 2 of workers only work half days, how long will it take them to complete the job?

So, actually it is equivalent as if THREE workers work full time.

Then it requires  = 56 days.


RELATED QUESTIONS

If it takes workers A and B 2 days to complete a job. And it takes workers B and C 3 days (answered by ankor@dixie-net.com)
If it takes 3 workers 15 days to complete a job, how long would it take 5 workers to... (answered by AnlytcPhil)
If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)
Working together, 4 skilled workers can complete a job in 5 days. However, 5 semi-skilled (answered by ankor@dixie-net.com)
The amount of time taken to build a house is inversely proportional to the number of... (answered by Alan3354)
Ten workers could do the job in 12 days. If 8 workers worked for 5 days and then half of... (answered by ankor@dixie-net.com)
how long will it take 8 workers to complete a job that took 5 workers to complete in 10... (answered by richwmiller)
How long will it take 4 workers to complete a task, given that it takes 6 days for 6... (answered by Simnepi)
it takes 12 workers 10 days to complete a piece of roadway how long will it take 5... (answered by richwmiller)